More wind turbines for Clyde wind farm

Posted on 16 Nov 2015 and read 4549 times
More wind turbines for Clyde wind farmSiemens (www.siemens.co.uk) has received an order for the supply, installation and commissioning of 54 direct-drive wind turbines.

The SWT-3.2-101 turbines will add another 172.8MW to SSE’s Clyde wind farm in South Lanarkshire, Scotland. Siemens will also be providing long-term service for the new Clyde Extension project.

With an existing capacity of 350MW, Clyde is already one of the largest onshore wind power plants in Europe.

The Clyde wind farm already has 152 operational turbines, making it the third-largest wind farm in Europe and SSE’s largest project to date. All of the existing turbines are Siemens 2.3MW units commissioned in 2011 and 2012.

The additional 54 turbines each have a capacity of 3.2MW and 101m-diameter rotors. The two-year construction project commenced in July 2015 and will support an estimated 500 local jobs through direct employment and the supply chain.

The 54 turbines are scheduled for delivery and installation from June 2016.

The Clyde Extension will be completed in June 2017.