Looking for a used or new machine tool?
1,000s to choose from
Machinery-Locator
Mills CNC MPU 2021 XYZ Machine Tools MPU Hurco MPU Bodor MPU Ceratizit MPU

Machinery-Locator
The online search from the pages of Machinery Market.

Deckel S 1 Tool and Cutter grinder 111145
Deckel S 1 Tool and Cutter grinder  

[Ref: 107681]
Deckel S 1 Tool and Cutter grinder [Ref: 107681] ...
Bowland Trading Ltd

Be seen in all the right places!

MMMA VILLAGE MACH 2024 MACH 2024 Metal Show & TIB 2024 Plastics & Rubber Thailand Intermach 2024 Metaltech 2024 Subcon 2024 Advanced Engineering 2024

AMRC carries out crucial validation tests

Posted on 09 May 2019 and read 3832 times
AMRC carries out crucial validation tests Crucial strength validation tests — the first of their kind in the UK — have been carried out on the reinforcement piles for a project to stabilise the cliffs behind the Scarborough Spa complex in Yorkshire.

The University of Sheffield AMRC’s Advanced Structural Testing Centre (ASTC) (www.amrc.co.uk) conducted the tests for piling specialist Keller UK, which has been contracted to make 206 concrete-filled steel piles for the £13.4 million stabilisation scheme.

The project requires 15m-long piles to be driven deep into the ground, but restricted access means that Keller must use shorter piles and connect them together.

To ensure that the connected piles are strong enough to withstand soil movement, Keller turned to the ASTC.

A custom rig was designed and built to carry out four-point bending strength tests on four two-tonne concrete-filled steel piles with varying wall thicknesses and collar lengths, to measure deflection in the middle of the tube, where the two sections are connected by a threaded collar.

The first tube tested had a 17mm wall thickness with a short collar, as this was deemed to be the weakest of the four samples. Phil Spiers, head of the ASTC, said the result was ‘very positive’.

It withstood a load of 1500kN (150 tonnes) bearing down on it and surpassed Keller’s target for displacement.

“We continued to test the other tubes, and they all passed well, giving Keller the validation and confidence it needed to proceed.”