Looking for a used or new machine tool?
1,000s to choose from
Machinery-Locator
Subcon MPU Baltec Mills CNC MPU 2021 Hurco MPU Ceratizit MPU

Machinery-Locator
The online search from the pages of Machinery Market.

Citizen A20 VIIPL CNC Swiss Multi-tasking Turning Centre (2008)
S/No. ACO 118 
(2008) 
Country of Origin: Japan,  
Maximum Spindle Speed 10,000rpm, 
10mm Maximu
S/No. ACO 118 (2008) Country of Origin: Japan, Maximum Spindle Speed 10,000rpm, 10mm Maximu...

Be seen in all the right places!

MACH 2026 Metal Show & TIB 2026 Plastics & Rubber Thailand Intermach 2026 METALTECH & AUTOMEX ITM Industry Europe 2026 Subcon 2026 Manufacturing Surabaya 2026

Big Carl ends the year on a high

Posted on 30 Dec 2022. Edited by: John Hunter. Read 2918 times.
Big Carl ends the year on a highStill wind conditions allowed engineers to carry out a massive lift at Hinkley Point C, overnight earlier this month (12 December). Big Carl, the world’s largest crane, lifted a 304-tonne steel liner ring onto the first reactor building in the early hours.

It is the third and final ring to be installed on the building, which will eventually contain one of Hinkley Point C’s two nuclear reactors. The unit has now grown in height by 11.6m and stands at 44m.

The liner ring, which was prefabricated in a factory on site, also features supporting brackets for the Polar Crane Beam. This internal crane will rotate 36deg above the reactor and be used for refuelling.

The reactor building now only has the ‘lid’ to be placed on top, with the iconic dome lift scheduled for next year.

Big Carl’s latest lift highlights the progress being made at Hinkley Point C, where teams are working 24/7 to get the plant operational as soon as possible. The power station will supply 6 million homes with clean, homegrown energy and is considered crucial in helping the UK avoid another energy crisis.